Processing and Issuance of Building Permit for Construction of Shared Passive Telecommunications Tower Infrastructure (PTTIs)
XI. Processing and Issuance of Building Permit for Construction of Shared Passive Telecommunications Tower Infrastructure (PTTIs)
A Building Permit is required before the construction of Shared Passive Telecommunications Tower Infrastructure (PTTIs). Permits supplementary to Building Permit for construction of PTTIs shall be applied and issued by the Building Official. These include Ancillary Permits and Accessory Permits (if applicable)
Office or Division : Office of the Municipal Engineer
Classification : Simple
Types of Transaction : G2C – Government to Client, G2G – Government to Government, G2B – Government to Business
Who may avail: Any individual, firm or corporation, government agency/instrumentality
Checklist of Requirements
Process
Step 1
Submit the duly notarized application form for Building Permit and other related documents as prescribed in the checklist
Agency Action :
1.1 Accepts the documents submitted and evaluate as to relevance and completeness.
1.2 The Building Official & other agencies evaluate the submitted documents. After verification and compliance of documentary requirements, Order of Payment will be prepared. If not, documents will be returned to applicant for corrections/compliance
Fees to be Paid: None
Processing Time :
1.1 30 minutes
1.2 6 days
Person Responsible:
1.1 Receiving Officer
1.2 Evaluation Team
Step 2
Receive the Order of Payment
Agency Action :
Prepare the Order of Payment and hand-in to the applicant
Fees to be Paid: None
Processing Time : 30 minutes
Person Responsible:
Building Official and Other members of Evaluation Team
Step 3
Pay the required fees and other charges at the designated cashiering area and surrender the official Receipt to the Receiving Section
Agency Action :
Receive the Official Receipt. The Building Official signs the Building Permit. Other head of agencies sign other clearances/certificates
Fees to be Paid: As prescribed in the NBCDO MC No. 1 s2004 (Please see the attached document)
Processing Time : 30 minutes
Person Responsible:
MTO Clerk
Step 4
Receive the Building Permit
Agency Action :
Releasing officer records important details of the Building Permit in the logbook and release to the applicant
Fees to be Paid: None
Processing Time : 30 minutes
Person Responsible:
Releasing officer
Total Time:
~
6 days 2 hours