Before an individual or a person, a firm or corporation, or any government agency or instrumentality construct, alter, repair, convert, use, occupy, move, demolish and add any building or structure, a Building Permit must be first obtained from the Office of the Municipal Engineer/Building Official. The prescribed application forms for building permit shall be used by all applicants. Building Permit is issued after the applicants’ submission of complete requirements and payment of necessary fees.
Office or Division : Office of the Municipal Engineer
Classification : Simple
Types of Transaction : G2C - Government to Client
Who may avail: Any individual, firm or corporation, government agency/instrumentality
Submit duly accomplished application forms and documentary requirements
Agency Action :
1.1 Receive the duly accomplished application forms and documentary requirements
1.2 The Building Official, the Zoning Officer and the BFP evaluate the plans forwarded by the receiving officer; three(3) sets will be provided to municipal Fire Marshal for review of fire safety requirements.
1.3 Return two (2) sets of plans: one (1) set to the Office of the Building Official and one (1) set to the applicant if evaluated and/or approved.
1.4 If disapproved, return the application forms and documentary requirements to the applicant for compliance based from the checklist provided
Fees to be Paid: None
Processing Time : 2 days
Person Responsible:
Representatives from Zoning Office, OBO and BFP
Receive the Order of Payment
Agency Action :
2.1 The Zoning Officer, the BFP and the Building Official simultaneously prepare and issue the Order of Payment to the applicant
Fees to be Paid: None
Processing Time : 15 minutes
Person Responsible:
Representatives from Zoning Office, OBO and BFP
Pay the necessary fees and charges in the designated cashiering area and surrender the Official Receipt to the receiving officer
Agency Action :
3.1 Receive the Official Receipt of payment
3.2 Consolidate all the clearances, certificates, and the Building Permit and its ancillaries
3.3 The Building Official sign and issue the Building Permit
Fees to be Paid: As contained in the National Building Code Development Office (NBCDO) Memorandum Circular No. 1 Series of 2004 dated November 4, 2004 RE: New Schedule of Building Permit Fees and Other Charges (Please see the attached document),
Fire Code of the Philippines,
Municipal Revenue Code
Processing Time : 30 minutes
Person Responsible:
Lorelie I. Magsino
Claim the Building Permit
Agency Action :
4.1 The releasing officer record the necessary information from the Building Permit in the logbook
4.2 Release the Building Permit
Fees to be Paid: None
Processing Time : 30 minutes
Person Responsible:
Lorelie I. Magsino
Radito Anoran
Total Time:
~
2 days, 1 hour, 15 minutes